Close Menu
MyGhanaDaily
    Facebook X (Twitter) Instagram
    MyGhanaDaily
    Tuesday, October 21
    Trending
    • Two nannies face criminal charges for drugging employer’s twin toddlers
    • Parliament reconvenes today
    • Fitch raises Ghana’s 2025 growth forecast to 4.9%
    • Volta Region’s Isabella Etornam Gagblezu Crowned Ghana’s Most Beautiful 2025
    • EOCO rescues 26 human trafficking victims in joint operation with QNET
    • Regional Maritime University hosts Laud Okantey Memorial Lecture
    • Zenith Bank Ghana holds health walk to mark 20th anniversary
    • Former NPA CEO and nine others now face 54 charges in OSP prosecution
    Your Marketplace Banner
    • News
    • Business
    • Entertainment
      • Music
      • Movies
      • Fashion
      • Celebrity news
    • Sports
    • Health
    • Technology
    • Agriculture
    • Opportunites
    • Videos
    • More
      • Education
      • Tourism
      • History
      • Feature
      • Opinion
      • World
    MyGhanaDaily
    Home»News»Pokuase interchange completion time now March 2021
    News

    Pokuase interchange completion time now March 2021

    myghanadailyBy myghanadailyNovember 12, 2020Updated:November 12, 2020No Comments3 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Untitled design 36

    Work on the four-tier Pokuase interchange at the ACP Junction in the Ga West Municipality, scheduled for completion in October this year, will now be completed in March 2021.

    The $84-million project, which was initially three-tier, was upgraded and work done on its present status is 87 per cent complete.

    Send your stories to Email: myghanadaily@gmail.com • WhatsApp: +233 577 145 140

    It is being jointly financed by the African Development Bank and the Government of Ghana.

    In an interview, Mr Kwabena Bempong, Associate Vice President of Associated Consultants Limited, a consulting company for the Pokuase Interchange and Local Roads, explained that a myriad of challenges hampered the progress of work on the project.

    “The coronavirus disease (COVID-19) pandemic affected the shipment of critical components for the project into the country and also some experts in China who were to come and supervise some aspects of the construction could not travel to the country,” he said.

    In addition, he said the additional work awarded by the government such as the construction of a 5-kilometre storm drain to reduce flooding at Pokuase, Ayawaso and Holy Hills, affected the schedule for the completion of the project.

    Mr Bempong indicated that the delay in the payment of compensation to the people affected by the project and heavy vehicular traffic on the Accra-Kumasi road undermined the scheduled completion of the project.

    “In view of this, we have written to the African Development Bank through the Ministry of Roads and Highways, for a six-month extension for the project,” he said, stressing that the “extension will not affect the cost of the project”.

    Currently, he said, the project was 87-per cent complete and work on the ten kilometres of local town roads was 99-per cent complete.

    Mr Bempong said the concrete overhead bridge for the Awoshie-Accra section had been completed, and the overhead bridge for the Kumasi-Kwabenya section was 98 per cent done, while the Awoshie-Kumasi section was 50-pr cent complete.

    He said the Kumasi-Accra section had been completed and opened to ease traffic on that stretch, especially during the Yuletide.

    The Resident Engineer said the Pokuase Interchange was the second biggest in Africa after the EB Cloete Interchange in South Africa and the biggest in West Africa.

    Mr Bempong expressed concern about speeding by some drivers on the Awoshie-Ablekuma road.

    He alleged that a woman was recently killed on that stretch and the traffic lights and road signs had been knocked down.

    Mr Bempong also disclosed that diesel poured on the Awoshie-Ablekuma road by some drivers who repaired their broken down vehicles on it was destroying the newly-constructed road.

    The Resident Engineer disclosed that the Ofankor to Nsawam dual carriageway had been awarded to Maripoma, a Ghanaian construction company, to construct it.

    Prior to the construction, he said, the company would do an overlay on the deplorable sections of the road to facilitate vehicular movement to address the heavy vehicular traffic on that stretch.

    Work on the Pokuase Interchange is being undertaken by Messrs China Zhongmei Engineering Company Limited and the interchange forms part of the Accra Urban Transport Project, aimed at promoting sustainable economic growth for the people in the area.

    The sod-cutting ceremony for work to start was performed in July, 2018.

    The interchange hosts an important international road, the Accra-Kumasi road, which links Accra to the Northern part of the country and Ghana to Sahelian countries such as Mali and Niger.

    Source: www.graphic.com.gh

    Send your news stories to
    Email: myghanadaily@gmail.com • WhatsApp: +233 577 145 140
    Advertise with us | Follow our WhatsApp channel for more news
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleGhana’s Economic situation self-inflicted-Economist
    Next Article Menzgold customers call for NAM1’s arrest over another attempt to scam them
    myghanadaily

    myghanadaily is managed by the Publishing Desk. You can reach us via email; info@myghanadaily.com

    Related Posts

    Two nannies face criminal charges for drugging employer’s twin toddlers

    October 21, 2025

    Parliament reconvenes today

    October 21, 2025

    Fitch raises Ghana’s 2025 growth forecast to 4.9%

    October 21, 2025
    LATEST NEWS
    • Two nannies face criminal charges for drugging employer’s twin toddlers
    • Parliament reconvenes today
    • Fitch raises Ghana’s 2025 growth forecast to 4.9%
    • Volta Region’s Isabella Etornam Gagblezu Crowned Ghana’s Most Beautiful 2025
    • EOCO rescues 26 human trafficking victims in joint operation with QNET
    SPORTS NEWS

    2026 FIFA WCQ: Ghana beats Mali

    September 9, 2025

    The Black Stars Podcast: A six-part dive into Ghana’s football history, struggles and sparks of glory

    August 30, 2025

    2026 World Cup qualifiers: Black Stars set to open camp on September 1

    August 27, 2025

    Felix Afena-Gyan Joins Amedspor on Season-Long Loan

    August 21, 2025

    Ayew Stays Positive as Foxes Target Quick Response

    August 21, 2025
    Recent Posts
    • Two nannies face criminal charges for drugging employer’s twin toddlers
    • Parliament reconvenes today
    • Fitch raises Ghana’s 2025 growth forecast to 4.9%
    • Volta Region’s Isabella Etornam Gagblezu Crowned Ghana’s Most Beautiful 2025
    • EOCO rescues 26 human trafficking victims in joint operation with QNET
    Like Us On Facebook
    Facebook Pagelike Widget
    • Facebook
    • Twitter
    • Instagram
    © 2019 -2025 Copyright | MyGhanaDaily.com

    Type above and press Enter to search. Press Esc to cancel.