Close Menu
MyGhanaDaily
    Facebook X (Twitter) Instagram
    MyGhanaDaily
    Tuesday, November 4
    Trending
    • Five Confirmed Dead in Fatal Crash at Asikuma Junction — GNFS
    • Santrokofi Bume Community Commissions Teachers’ Quarters
    • NSMQ 2025: Opoku Ware joins Mfantsipim, Augustine’s in grand finale
    • Tree Crops Development Authority Inaugurates Audit Committee
    • Cape Coast Teaching Hospital launches laparoscopic services
    • DBS Industries Supports Renovation of Sunyani Central Prisons Canteen Pergola
    • Anglican Men’s Fellowship Holds 7th Quadrennial Conference, Elects New National Executives
    • Why the UAE’s ADNOC Should Be Ghana’s Strategic Partner to Accelerate Exploration in the Voltaian Basin
    Your Marketplace Banner
    • News
    • Business
    • Entertainment
      • Music
      • Movies
      • Fashion
      • Celebrity news
    • Sports
    • Health
    • Technology
    • Agriculture
    • Opportunites
    • Videos
    • More
      • Education
      • Tourism
      • History
      • Feature
      • Opinion
      • World
    MyGhanaDaily
    Home»News»VRA announces major renovation of Kpong Dam after 40 years
    News

    VRA announces major renovation of Kpong Dam after 40 years

    myghanadailyBy myghanadailyOctober 28, 2024No Comments3 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Economy Dam Rehabilitation
    Getting your Trinity Audio player ready...

    The Volta River Authority (VRA), has announced the renovation of the 160-megawatt hydroelectric Kpong Dam and spillway gates in Akuse in the Eastern Region, after more than 40 years of its construction.

    The announcement was made at a stakeholders’ engagement meeting that included chiefs, assembly members, and opinion leaders from Akuse, Torgome, Fodzoku, Natriku, and surrounding areas.

    Send your stories to Email: myghanadaily@gmail.com • WhatsApp: +233 577 145 140

    The meeting, which discussed implications of the project, aimed to elicit ideas from the communities about their concerns and ways to mitigate the project’s potential positive and negative impacts.

    In an interview with the Ghana News Agency, Mr. Kwaku Wiafe, VRA’s Director of Engineering Services, explained the goal of engaging stakeholders and community members, saying, it was meant to inform them about the planned Kpong Dam restoration project.

    He explained that the project aimed to rehabilitate the dyke because the dam was a rock-filled dam. Through the action of water waves on the rocks over 40 years, some of them had  been displaced along the entire length.

    He stated that they initially intended to repair it, but they soon realized that adding a fresh layer of rocks would transform it into a new dam, extending its lifespan.

    “Since the dam at Akuse only permits water from Akosombo to pass and if the water is coming from Akosombo, the spillway must be prepared to allow it to pass, otherwise it will overtop it, which is why we must ensure that our spillways are extremely dependable in light of climate change and other issues,” he said.

    He added that “So the reliability of the spillways is critical to the dam’s safety, and by improving the stability of the dyke and the reliability of the spillways, the overall safety of the dam is enhanced, which goes a long way towards protecting both downstream communities and ensuring that the asset’s integrity is maintained so that Ghanaians can continue to benefit from a reliable power supply.”

    In addition, the director said that VRA was also going to rehabilitate the deplorable 10-kilometre road from Okwenya Junction to Akuse for haulage trucks and other motor vehicles.

    He mentioned that this decision came after agitation from both VRA staff, the natives of Akuse, and other motorists. The road would be improved into a first-class road.

    Some of the stakeholders raised concerns about some fish species going extinct and potential water pollution but in response, Mr. Wiafe explained that the way and manner the  work was going to be done would not cause water pollution.

    It would not also affect fishing because they were not going to use the fishing landing site, and also those that haulage trucks would not be allowed to go beyond 15 kilometres per hour speed limit.

    The road would be watered regularly to suppress dust.

    Mr. Emmanuel Darko Thompson, a civil engineer at VRA, stated in a presentation that they intended to restore the upstream dykes as well as the spillway gate.

    He noted that the objective was not to replace the gate, but rather to restore it, particularly the corroded gates.

    He mentioned that they had planned to restore the dykes with 150,000 cubic meters of rocks.

    “If we don’t repair the dam’s dykes and it collapses, it will impact everyone in the nation as well as productivity and economic growth,” he added.

    Mr. Ibrahim Mahama, the assembly member for Akuse, urged the VRA to extend the road restoration project to Asutuare

    Source: GNA

    Send your news stories to
    Email: myghanadaily@gmail.com • WhatsApp: +233 577 145 140
    Advertise with us | Follow our WhatsApp channel for more news
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleBagbin rallies Speakers of African Parliaments to fight poverty
    Next Article Genius IT Foundation Hosts Cybersecurity Awareness Month Conference
    myghanadaily

    myghanadaily is managed by the Publishing Desk. You can reach us via email; info@myghanadaily.com

    Related Posts

    Five Confirmed Dead in Fatal Crash at Asikuma Junction — GNFS

    November 4, 2025

    Santrokofi Bume Community Commissions Teachers’ Quarters

    November 4, 2025

    NSMQ 2025: Opoku Ware joins Mfantsipim, Augustine’s in grand finale

    November 4, 2025
    LATEST NEWS
    • Five Confirmed Dead in Fatal Crash at Asikuma Junction — GNFS
    • Santrokofi Bume Community Commissions Teachers’ Quarters
    • NSMQ 2025: Opoku Ware joins Mfantsipim, Augustine’s in grand finale
    • Tree Crops Development Authority Inaugurates Audit Committee
    • Cape Coast Teaching Hospital launches laparoscopic services
    SPORTS NEWS

    2026 FIFA WCQ: Ghana beats Mali

    September 9, 2025

    The Black Stars Podcast: A six-part dive into Ghana’s football history, struggles and sparks of glory

    August 30, 2025

    2026 World Cup qualifiers: Black Stars set to open camp on September 1

    August 27, 2025

    Felix Afena-Gyan Joins Amedspor on Season-Long Loan

    August 21, 2025

    Ayew Stays Positive as Foxes Target Quick Response

    August 21, 2025
    Recent Posts
    • Five Confirmed Dead in Fatal Crash at Asikuma Junction — GNFS
    • Santrokofi Bume Community Commissions Teachers’ Quarters
    • NSMQ 2025: Opoku Ware joins Mfantsipim, Augustine’s in grand finale
    • Tree Crops Development Authority Inaugurates Audit Committee
    • Cape Coast Teaching Hospital launches laparoscopic services
    Like Us On Facebook
    Facebook Pagelike Widget
    • Facebook
    • Twitter
    • Instagram
    © 2019 -2025 Copyright | MyGhanaDaily.com

    Type above and press Enter to search. Press Esc to cancel.